The bond oversight committee on tour of High Plains

On Thursday, June 27, Orange Live joined the Bond Construction Oversight Committee at High Plains Community Center for a tour of the South Wing and Pool renovation projects.

Anyone who spent time in the South wing for meetings or during the annual train show may remember that the tiled walls were a highly glossed beige.

Since, they were sanded down, prepped and re-painted green. In May, the committee noted that the paint was peeling from the walls in multiple locations. The painting contractor was fired and a new one hired to complete the job.

There are two large areas that had formerly been two rooms, but the dividing walls were knocked down. They are now waiting for Accordion dividers so organizations can make the meeting spaces smaller when necessary.

The men’s and women’s bathrooms have been completely renovated and are bright, clean and modern.

In May, the Pool Locker Room schedule was updated showing the start of tile work on June 5. Floors were puddling badly in the men’s and family locker rooms and were reconfigured for better drainage.

Committee member Mitch Goldblatt, an Orange selectman, said he was disappointed that the job hadn’t been completed before the Recreation Department’s camp program started. He added that the Nursery School should be able to open again in late August.

From what we observed during the tour, we think everyone will be pleased with the “New” and improved High Plains Community Center.